Seven people need 90 days to repair and paint a heritage building. if the job should be completed in 15 days. how many more people need to be employed.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
65% of students in your school participate in at least one after school activity. if there are 980 students in you school, how many do not participate in an after school activity?
Answers: 1
question
Mathematics, 21.06.2019 19:30
What is the lcm of 16 and 40 ? 24 and 40 ?
Answers: 2
question
Mathematics, 21.06.2019 20:00
I’m stuck on this equation, anyone got the answer?
Answers: 1
question
Mathematics, 21.06.2019 22:30
Kevin's bank offered him a 4.5% interest rate for his mortgage. if he purchases 3 points, what will be his new rate?
Answers: 2
You know the right answer?
Seven people need 90 days to repair and paint a heritage building. if the job should be completed in...
Questions
question
Mathematics, 27.04.2020 02:12
question
Mathematics, 27.04.2020 02:12
question
Mathematics, 27.04.2020 02:12
question
Physics, 27.04.2020 02:12
Questions on the website: 13722363