Mathematics, 10.11.2019 05:31 jholland03

Suppose that the design engineering team set the specifications for length of a stamped sheet-metal part at 10 inches (d) with acceptable tolerances of ±.05 inches (usl and lsl). the average length of the products produced by the actual stamping process is 9.99 inches (m) with a standard deviation of .015 inches (s). the calculations for the cp and cpk are as follows: a. cp = (10.05-9.95)/6(.015) = .10/.09 = 1.11b. k = (10 – 9.99)/((10.05-9.95)/2) = .01/.05 = .20
c. cpk = 1.11 (1-.20) = 1.11(.8) = .88

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:30
Find the area of the triangle formed by the origin and the points of intersection of parabolas y=−3x^2+20 and y=x^2−16.
Answers: 3
question
Mathematics, 22.06.2019 02:00
Hannah reads at a constant rate of 33 pages every 88 minutes. write an equation that shows the relationship between pp, the number of pages she reads, and mm, the number of minutes she spends reading.
Answers: 1
question
Mathematics, 22.06.2019 05:10
In triangle abc, w is the centroid and be = 9. find bw. a. 3 b. 6 c. 9 d. 18
Answers: 2
question
Mathematics, 22.06.2019 05:40
Abookstore owner is having a sale the book bart wants was originally priced at $14.99 the book is now $10.04 by what percentage was the price reduced
Answers: 1
You know the right answer?
Suppose that the design engineering team set the specifications for length of a stamped sheet-metal...