You have a programming budget of 30 five-day man weeks for a project .you work at a rate of 60 man hours per two week iteration. how many weeks would it to finish the project? (there are 40 man hours in a week)

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:10
Which system of linear inequalities is graphed? can somebody pleasssse
Answers: 3
question
Mathematics, 21.06.2019 15:30
For one history test, keith had to answer 40 questions. of these 40 questions, keith answered 28 of them correctly. what percent did keith get on his history test? round your answer to the nearest tenth if necessary
Answers: 1
question
Mathematics, 21.06.2019 19:50
Which inequality is equivalent to -3x < -12? x < 4 , x < -4 , x > 4, x > -4
Answers: 1
question
Mathematics, 21.06.2019 23:00
Jorge wants to determine the enlarged dimensions of a digital photo to be used as wallpaper on his computer screen. the original photo was 800 pixels wide by 600 pixels high. the new photo will be 1,260 pixels wide. what will the new height be?
Answers: 1
You know the right answer?
You have a programming budget of 30 five-day man weeks for a project .you work at a rate of 60 man h...
Questions
question
World Languages, 17.09.2019 17:30
Questions on the website: 13722363