you work as a librarian for a local community college. a
recent report on publishing project shows that show that
57.75% of the project has been completed in the past 7
work days. if work continues at the same rate,
approximately how many work days will be required in
total for the entire project?
your answer

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
David must install fencing around a lot that is shaped like a right angle.the side of lot that runs east-west is 200 ft long.the side of the lot runs north-south is 125 ft long.calculate how many feet of fencing he will need to surround the entire lot.
Answers: 2
question
Mathematics, 22.06.2019 01:50
The area of each triangle is 7 square units. the surface area of the triangular prism is
Answers: 1
question
Mathematics, 22.06.2019 03:00
Luigi is the first person to finish a 5k race and is standing 13 feet beyond the finish line. another runner, mario, is still running the race and has approximately 24 feet before he reaches the finish line. what is the distance between mario and luigi? explain through words, numbers or pictures how you found the answer.
Answers: 1
question
Mathematics, 22.06.2019 04:30
Ahyperbola centered at the origin has a vertex at (-6,0) and a focus at (10,0). what are the directrices?
Answers: 3
You know the right answer?
10 poi
you work as a librarian for a local community college. a
recent report on publish...
Questions
question
Mathematics, 09.12.2020 20:20
question
Mathematics, 09.12.2020 20:20
question
Mathematics, 09.12.2020 20:20
question
Mathematics, 09.12.2020 20:20
Questions on the website: 13722363