The cost, c, to produce b baseball bats per day is modeled by the function c(b) = 0.06b2 – 7.2b + 390. what number of bats should be produced to keep costs at a minimum?
27 bats
60 bats
174 bats
390 bats

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Jabari is power washing houses for a summer job. for every job, he charges an initial fee plus $30 for each hour of work. his total fee for a 4 -hour job, for instance, is $170 . jabari's total fee,f, for a single job is a function of the number,t, of hours it takes him to complete the job. write the function's formula.
Answers: 2
question
Mathematics, 21.06.2019 18:00
Need on this geometry question. explain how you did it.
Answers: 1
question
Mathematics, 21.06.2019 18:40
Which of the following represents the range of the graph of f(x) below
Answers: 1
question
Mathematics, 21.06.2019 21:40
The number of chocolate chips in a bag of chocolate chip cookies is approximately normally distributed with a mean of 12611261 chips and a standard deviation of 118118 chips. (a) determine the 2626th percentile for the number of chocolate chips in a bag. (b) determine the number of chocolate chips in a bag that make up the middle 9696% of bags. (c) what is the interquartile range of the number of chocolate chips in a bag of chocolate chip cookies?
Answers: 2
You know the right answer?
The cost, c, to produce b baseball bats per day is modeled by the function c(b) = 0.06b2 – 7.2b + 39...
Questions
question
Mathematics, 27.01.2021 21:50
question
Mathematics, 27.01.2021 21:50
Questions on the website: 13722367