Randy can rebuild an automobile engine in a hours. alvin can rebuild the same engine in b hours. if randy and alvin work together at their respective rates to rebuild the engine, which of the following represents the portion of the job that randy will not have to complete?
a. ab/(a+b)
b. (a-b)/(a+b)
c. b/(b-a)
d. a/(a+b)
e. b/(a+b)

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:40
Imagine a new pasture with grass growing on it. every day after the seeds have germinated, the number of blades of grass in the pasture triples. after 18 days, the entire pasture is completely covered in grass. how many days did it take for the pasture to be one-third covered in grass?
Answers: 2
question
Mathematics, 21.06.2019 17:30
Which of the following is correct interpretation of the expression -4+13
Answers: 2
question
Mathematics, 21.06.2019 21:00
How do i put 3(x+7) in distributive property
Answers: 1
question
Mathematics, 21.06.2019 21:50
Which rule describes the composition of transformations that maps ajkl to aj"k"l"? ro. 900 o to, -2(x, y) to, -20 ro, 900(x, y) ro, 9000 t-2. o(x,y) t-2, 00 ro, 900(x, y)
Answers: 2
You know the right answer?
Randy can rebuild an automobile engine in a hours. alvin can rebuild the same engine in b hours. if...
Questions
question
Mathematics, 21.04.2020 04:23
question
Spanish, 21.04.2020 04:23
Questions on the website: 13722367