You work as a coordinator for data entry projects. on one project, the status shows that 15% of the work was completed in 6 days. if the work progresses at the same rate, how many more days will be required to complete the remainder of the project.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Plz ! what is the volume of this pyramid? with numbers of 30cm 14cm 18cm
Answers: 1
question
Mathematics, 21.06.2019 14:40
How many square feet of out door carpet will we need for this hole? 8ft 3ft 12ft 4ft
Answers: 1
question
Mathematics, 21.06.2019 20:00
What does the sign of the slope tell you about a line?
Answers: 2
question
Mathematics, 21.06.2019 22:30
How do you do the foil method with polynomials?
Answers: 1
You know the right answer?
You work as a coordinator for data entry projects. on one project, the status shows that 15% of the...
Questions
question
Biology, 11.03.2021 23:10
question
SAT, 11.03.2021 23:10
question
Mathematics, 11.03.2021 23:10
Questions on the website: 13722365