Mathematics, 25.12.2019 14:31 130004979

Two workers, if they were working together, could finish a certain job in 12 days. if one of the workers does the first half of the job and then the other one does the second half, the job will take them 25 days. how long would it take each worker to do the entire job by himself?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
The measure of an angle is 117°. what is the measure of a supplementary angle?
Answers: 2
question
Mathematics, 21.06.2019 19:50
A3-dimensional figure has a square base and 4 lateral faces that meet at a point. explain the difference between the cross sections when a slice is made perpendicular to the base through the vertex, and when a slice is made perpendicular to the base and not through the vertex
Answers: 2
question
Mathematics, 21.06.2019 20:00
Graph the linear function using the slooe and y intercept
Answers: 2
question
Mathematics, 22.06.2019 00:10
Which of these would have been most likely to have been a carpetbagger during the reconstruction era? a) a new york businessman who relocated to mississippi b) a former slave who was able to buy land in birmingham c) a carolina-born politician who supported the democratic d) a former confederate officer who owned a farm in memphis eliminate
Answers: 1
You know the right answer?
Two workers, if they were working together, could finish a certain job in 12 days. if one of the wor...