The time to complete a project varies inversely with the number of employees. if 3 people can complete the project in 7 days, how long will it take 5 people?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
In trapezoid efgh, m∠gfe=63∘. identify m∠ghe. !
Answers: 2
question
Mathematics, 21.06.2019 16:00
Select the correct answer. joshua likes to read. he read 6 books when he was 6 years old. every year he doubled the number of books he read the previous year. how many total books did he read between the ages of 6 and 10? a. 60 b. 90 c.186 d.187
Answers: 1
question
Mathematics, 21.06.2019 17:30
For each proportion find the unknown number x 1/5/8=×/15
Answers: 1
question
Mathematics, 21.06.2019 19:00
15 points! write the slope-intercept form of the equation of the line through the given point with the given slope. use y-y = m(x-x) to solve. through (2,5) slope= undefined
Answers: 2
You know the right answer?
The time to complete a project varies inversely with the number of employees. if 3 people can comple...
Questions
question
Health, 19.05.2020 12:57
question
Mathematics, 19.05.2020 12:57
question
Mathematics, 19.05.2020 12:57
question
Mathematics, 19.05.2020 12:58
Questions on the website: 13722367