Which option identifies the section of the project charter represented in the following scenario?
For the past five years, students at New School have been
in desperate need of a playground. The closest
playground is a mile away, at Safe Park. Our project is to
design a playground for the students and to find funding
in the community to support it.
project development cycle
executive summary
O project objectives
O
constraints

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 03:10
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
question
Engineering, 04.07.2019 18:10
Which of the following components of a pid controlled accumulates the error over time and responds to system error after the error has been accumulated? a)- proportional b)- derivative c)- integral d)- on/off.
Answers: 2
question
Engineering, 04.07.2019 18:10
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
question
Engineering, 04.07.2019 19:10
A)-explain briefly the importance of standards in engineering design. b)- what is patent? c)-explain the relationship between these standards: b.s. and b.s.en d)- in engineering design concepts, types of loads and how they act are important factors. explain.
Answers: 3
You know the right answer?
Which option identifies the section of the project charter represented in the following scenario?
Questions
question
Social Studies, 15.11.2019 04:31
Questions on the website: 13722361