The amount of time an activity can be delayed and yet not delay the project is termed: A. Total slack.
B. Free slack.
C. Critical float.
D. Float pad.
E. Slip pad.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The temperature of air decreases as it is compressed by an adiabatic compressor. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:10
Afull journal bearing has a journal diameter of 27 mm, with a unilateral tolerance of -0.028 mm. the bushing bore has a diameter of 27.028 mm and a unilateral tolerance of 0.04 mm. the l/d ratio is 0.5. the load is 1.3 kn and the journal runs at 1200 rev/min. if the average viscosity is 50 mpa-s, find the minimum film thickness, the power loss, and the side flow for the minimum clearance assembly.
Answers: 1
question
Engineering, 04.07.2019 18:10
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
question
Engineering, 04.07.2019 18:20
Most leaks in reciprocating air compressors can be detected and minimized by: (clo4) a)-detecting leakage areas using ultrasonic acoustic detector. b)-tightening joints and connections c)-replacing faulty equipment d)-all of the given options
Answers: 2
You know the right answer?
The amount of time an activity can be delayed and yet not delay the project is termed: A. Total sla...
Questions
question
Mathematics, 20.03.2021 07:20
question
Mathematics, 20.03.2021 07:20
question
Biology, 20.03.2021 07:20
Questions on the website: 13722367