A contractor has one mechanical excavator and one bulldozer, which are available for work on either of two adjacent sites. On one site, clay overburden is being excavated for a ballast pit owner, and on the other, ballast is being removed under subcontract to another client. Experience tell s the contractor that $50 profit can be made for 1000 m3 of clay overburden and $60 profit for every 1000 m3 of ballast removed. A comprehensive work study assesses the resources required to remove 1000 m3 of clay to be 8 hours' use of the excavator, 4 hours' use of the bulldozer and 50 man-hours of operatives' time. In the case of the excavation of 1000 m3 of ballast, the resources are required for 4 hours, 5 hours, and 13 man-hours, respectively. The contractor's employees work a 40- hour week. The mechanical equipment is also available for a 40-hour week. In addition to the mechanical equipment, 5 laborers are available for up to 40 hours each in any one week in order to assist with the work. When they are not employed on the excavation, use can be made of the operatives' elsewhere. Write a linear programming formulation for maximizing profit during one working week. The unknowns are: X1 = Units of 1000 m3 of clay excavated X2 = Units of 1000 m3 of ballast excavated

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The mass flow rate of the fluid remains constant in all steady flow process. a)- true b)- false
Answers: 1
question
Engineering, 04.07.2019 18:10
An ideal otto cycle with air as the working fluid has a compression ratio of 8. the minimum and maximum temperatures in the cycle are 300 k and 1340 k. use constant specific heats at room temperature to determine (a) the amount of heat transferred to the air during the heat- addition kj/kg, (b) the thermal efficiency, and (c) the thermal efficiency of a carnot cycle ope limits. process, in rating between the same temperature
Answers: 2
question
Engineering, 04.07.2019 18:20
Vibration monitoring this technique uses the noise or vibration created by mechanical equipment and in seme cases by plant systems to detemine their actual condtion. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:20
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
You know the right answer?
A contractor has one mechanical excavator and one bulldozer, which are available for work on either...
Questions
question
Mathematics, 03.07.2020 19:01
question
Mathematics, 03.07.2020 19:01
Questions on the website: 13722367