1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update schedule indicates that a delay of 9 days has been experienced in the execution of Activity B and that a delay to the start of Activity D has consumed this activity’s “free float”. Clearly provide answers (numeric figures accompanied by clear explanations regarding the basis of the numeric figures) to the following:

a) What is the “now” projected total project duration and what drives this new figure

b) Explain the change (if any) to the total float of Activity L?

c) How much free and total floats can still be enjoyed by Activity D?

d) Given the delays described above, and provided that Activities C and F are shown to have been completed but with a joint consumption of 4 out of the 7 days of total float that were originally available to the C-F-K activity chain: (i) what interference (in days) to the scheduling of Activity K can be solely attributed to the completed execution of Activity B? (3 points) And, (ii) what total float can still be enjoyed by Activity K?

2- Given the delay reported to have taken place to the start of Activity D and the flexibility (if any) being now enjoyed (currently under the updated schedule), please argue what circumstances would warrant that the contractor’s PM, in consultation with his site-management subordinates, considers adopting a revised method of work, crew assignment (no. of crews), and/or work-shift schedule, and whether any one or more of these circumstances is/are evident in the updated schedule in connection with the scheduling results newly computed for D.

3- Assume the total duration for the project under study is expressed in months, totaling 14 months, on the basis of adopting a DBB project delivery approach. When will an estimate of this overall duration have been first made? And, what kind of control will be needed regarding this 14-month duration if the owner decides to switch to the “CM at Fee” approach at the point of time when the design phase has reached around 30% completion?

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 12:10
On a average work day more than work place firs are reorted
Answers: 1
question
Engineering, 04.07.2019 18:10
Air is to be cooled in the evaporator section of a refrigerator by passing it over a bank of 0.8-cm-outer-diameter and 0.4-m-long tubes inside which the refrigerant is evaporating at -20°c. air approaches the tube bank in the normal direction at 0°c and 1 atm with a mean velocity of 4 m/s. the tubes are arranged in-line with longitudinal and transverse pitches of sl- st 1.5 cm. there are 30 rows in the flow direction with 15 tubes in each row. determine (a) the refrigeration capacity of this system and (b) pressure drop across the tube bank. evaluate the air properties at an assumed mean temperature of -5°c and 1 atm. is this a good assumption?
Answers: 1
question
Engineering, 04.07.2019 19:20
Air at a pressure of 1atm and a temperature of 40 c is in parallel flow over the top surface of a flat plate that is heated to a uniform temperature of 120 c. the plate has a length of 0.40m (in the flow direction) and a width of 0.15m. the reynolds number based on the plate length is 50, 000. what is the rate of heat transfer from the plate to the air? if the free stream velocity of the air is doubled and the pressure is increased to 10 atm what is the rate of heat transfer?
Answers: 2
question
Engineering, 06.07.2019 02:30
Define thermoplastic polymers and thermosetting polymers in terms of their structures, and (ii) describe briefly a process suitable for the production of products from each type of polymer.
Answers: 3
You know the right answer?
1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update...
Questions
question
World Languages, 03.11.2019 03:31
question
Mathematics, 03.11.2019 03:31
question
Chemistry, 03.11.2019 03:31
Questions on the website: 13722362