subject
Engineering, 13.05.2020 13:57 salvadorperez26

Giant Equipment Ltd. is considering two projects to invest next year. Both projects have the same
start-up costs. Project A will produce annual cash flows of $42,000 at the beginning of each year for
eight years. Project B will produce cash flows of $48,000 at the end of each year for seven years. The
company requires a 12% return.
Required:
a) Which project should the company select and why?
b) Which project should the company select if the interest rate is 14% at the cash flows in Project B
is also at the beginning of each year?

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Awall of 0.5m thickness is to be constructed from a material which has average thermal conductivity of 1.4 w/mk. the wall is to be insulated with a material having an average thermal conductivity of 0.35 w/mk so that heat loss per square meter shall not exceed 1450 w. assume inner wall surface temperature of 1200°c and outer surface temperature of the insulation to be 15°c. calculate the thickness of insulation required.
Answers: 3
question
Engineering, 04.07.2019 18:20
Avolume of 2.65 m3 of air in a rigid, insulated container fitted with a paddle wheel is initially at 264 k, 5.6 bar. the air receives 432 kj by work from the paddle wheel. assuming the ideal gas model with cv = 0.71 kj/kg • k, determine for the air the amount of entropy produced, in kj/k
Answers: 2
question
Engineering, 04.07.2019 19:10
What is a monomer? how do they form a ploymer from the view point of chemical bonding?
Answers: 1
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
Giant Equipment Ltd. is considering two projects to invest next year. Both projects have the same
Questions
question
Mathematics, 20.10.2020 20:01
question
Mathematics, 20.10.2020 20:01
question
Mathematics, 20.10.2020 20:01
Questions on the website: 13722363