Two activated sludge aeration tanks at Turkey Run, Indiana, are operated in series. Each tank has the following dimensions: 7.0 m wide by 30.0 m long by 4.3 m effective liquid depth. The plant operating parameters are as follows:
Flow = 0.0796 m3/s
Soluble BOD5 after primary settling = 130mg/L
MLVSS = 1.500 mg/L
MLSS = 1.40 (MLVSS)
Settled sludge volume after 30 min = 230.0 mL/L
Determine the following: aeration period, F/M ratio, SVI

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:20
Most leaks in reciprocating air compressors can be detected and minimized by: (clo4) a)-detecting leakage areas using ultrasonic acoustic detector. b)-tightening joints and connections c)-replacing faulty equipment d)-all of the given options
Answers: 2
question
Engineering, 04.07.2019 18:20
What is the heat treatment of metals? what is the benefit of it? why and how it's useful? answer in details, do not write by hand.
Answers: 3
question
Engineering, 04.07.2019 18:20
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
question
Engineering, 04.07.2019 19:10
What is a monomer? how do they form a ploymer from the view point of chemical bonding?
Answers: 1
You know the right answer?
Two activated sludge aeration tanks at Turkey Run, Indiana, are operated in series. Each tank has th...
Questions
question
Mathematics, 17.12.2020 18:10
question
Mathematics, 17.12.2020 18:10
question
Mathematics, 17.12.2020 18:10
question
Business, 17.12.2020 18:10
Questions on the website: 13722363