A truck with heaped capacity of 10 cy is used to disposed to excavated material at dumpsite of 5 miles from the job site. The average velocity of the is 30 mph. The dump time is 30 second and load time is 50 second. Determine the production capacity of the dump truck.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Heat is added to a piston-cylinder device filled with 2 kg of air to raise its temperature 400 c from an initial temperature of t1 27 cand pressure of pi 1 mpa. the process is isobaric process. find a)-the final pressure p2 b)-the heat transfer to the air.
Answers: 1
question
Engineering, 04.07.2019 18:10
Draw the engineering stress-strain curve for (a) bcc; (b) fcc metals and mark important points.
Answers: 1
question
Engineering, 04.07.2019 19:20
Air enters a horizontal, constant-diameter heating duct operating at steady state at 290 k, 1 bar, with a volumetric flow rate of 0.25 m°/s, and exits at 325 k, 0.95 bar. the flow area is 0.04 m2. assuming the ideal gas model with k = 1.4 for the air, determine (a) the velocity at the inlet and exit, each in m/s, and (c) the rate of heat transfer, in kw flow rate, in kg/s, (b) the mass kg 0.3
Answers: 2
question
Engineering, 06.07.2019 03:20
Aload of 10kn is to be suddenly applied to the free end of a vertical rod of length 500 mm, the upper end being rigidly fixed. 190 mechanical science what should the diameter of the rod be if the maximum stress in the rod is not to exceed 100 mpa? the tensile modulus of the rod is 205 gpa.
Answers: 2
You know the right answer?
A truck with heaped capacity of 10 cy is used to disposed to excavated material at dumpsite of 5 mil...
Questions
question
History, 07.06.2020 02:00
Questions on the website: 13722363