During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective) parts and 17 defective parts were produced. The operation cycle consists of a processing time of 5.23 min, and a part handling time of 0.58 min. Every 50 parts, a tool change is performed, and this takes 4.2 min. The machine experienced several breakdowns during the week.
Determine
(a) hourly production rate of acceptable parts,
(b) scrap rate, and
(c) availability (proportion uptime) of the machine during this week.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Afluid flows with a velocity field given by v=(x/t)i.. determine the local and convective accelerations when x=3 and t=1.
Answers: 2
question
Engineering, 04.07.2019 18:10
Courses that are developed by subject matter experts, internal or extemal to the college or university. these programs are marketed by the school (clo2) marks a)-vocational schools b)-vendor training c)-colleges & universities d)-continuing education programs
Answers: 2
question
Engineering, 04.07.2019 19:10
What is a monomer? how do they form a ploymer from the view point of chemical bonding?
Answers: 1
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective)...
Questions
question
Mathematics, 16.03.2020 05:38
question
History, 16.03.2020 05:38
question
History, 16.03.2020 05:39
question
Geography, 16.03.2020 05:39
question
Mathematics, 16.03.2020 05:41
Questions on the website: 13722367