The transportation department plans to build a new high-speed train route between two cities. The transportation department wants to implement a simulation of the train before any construction begins on this project. Which of the following statements is true about the use of a simulation for this project?
a. A simulation cannot be used to test the train under varying weather conditions.
b. Implementing a simulation is likely to increase the overall costs associated with the project.
c. Other high-speed train routes have been constructed in other locations, so a simulation is not needed.
d. Using a simulation may expose potential safety issues that can be corrected before construction begins.
Answers: 1
Computers and Technology, 24.06.2019 08:00
How can smart devices benefit businesses, organizations, and social communities in the global marketplace?
Answers: 1
Computers and Technology, 24.06.2019 13:00
Refer to the figure and match the theorem that supports the statement.1.if chords are =, then arcs are =.if bc = de, then arc bc = arc de2.if arcs are =, then chords are =.if arc bc = arc de, then bc = de3.diameters perpen
Answers: 3
Computers and Technology, 24.06.2019 13:30
To move an excel worksheet tab, simply right-click on it drag and drop it double-click on it delete it
Answers: 1
Computers and Technology, 24.06.2019 16:00
Your is an example of personal information that you should keep private.
Answers: 1
The transportation department plans to build a new high-speed train route between two cities. The tr...
Biology, 21.05.2020 15:57
Computers and Technology, 21.05.2020 15:57
Mathematics, 21.05.2020 15:57
Mathematics, 21.05.2020 15:57
History, 21.05.2020 15:57
Mathematics, 21.05.2020 15:57
Mathematics, 21.05.2020 15:58
Mathematics, 21.05.2020 15:58
Chemistry, 21.05.2020 15:58
Mathematics, 21.05.2020 15:58