Need help:((. I’ll mark brainliest if correct Select the correct answer.
Which statement is true with regard to project scheduling?

A. Scheduling in plan-based processes does not change with the progress of the project.

B. Plan-based processes use an iterative approach for scheduling each phase of the project.

C. Scheduling in an agile process involves planning the short-term phases of a project.

D. Agile processes require less detail than plan-based processes do in an initial project schedule.

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 03:30
How can you repin an image on your pinterest pin board a. click on the "repin" button b. click on the "add pin" button c. click on the "upload a pin" button d. click on the "save pin" button.
Answers: 2
question
Computers and Technology, 23.06.2019 14:30
The basic work area of the computer is it screen that you when you first fire up your computer
Answers: 1
question
Computers and Technology, 24.06.2019 03:30
Explain the importance of html in web page designing in 20 sentences..
Answers: 1
question
Computers and Technology, 24.06.2019 20:30
Drums installed, you would apply clicks of the parking brake to obtain a slight drag on both rear wheels
Answers: 1
You know the right answer?
Need help:((. I’ll mark brainliest if correct Select the correct answer.
Which statement is t...
Questions
question
Mathematics, 06.11.2020 17:20
question
Mathematics, 06.11.2020 17:20
question
SAT, 06.11.2020 17:20
Questions on the website: 13722367