subject

A project team using a linear, sequential model builds a software application over a long duration. All activities in the project are carried out one after the other. Once the product is tested, the team installs the application. Which phase of this model involves installation? A.
system design
B.
coding
C.
deployment
D.
requirements gathering
E.
testing

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 21:00
The mode is generally used when delivering a presentation to an need now
Answers: 1
question
Computers and Technology, 23.06.2019 04:00
Laire writes a letter to her grandmother, in which she describes an amusement park she visited last week. she adds pictures of that place in her letter. which feature of a word processing program will claire to remove unwanted parts of the pictures?
Answers: 3
question
Computers and Technology, 23.06.2019 09:30
After you present a proposal, the committee starts asking you questions, some beyond the strict focus of your proposal. they ask questions about implications in other fields and knowledge about other fields. you are asked to redo your proposal. what is most likely missing? breadth of material depth of material clarity of material details of material
Answers: 1
question
Computers and Technology, 23.06.2019 18:40
Johnson enterprises uses a computer to handle its sales invoices. lately, business has been so good that it takes an extra 3 hours per night, plus every third saturday, to keep up with the volume of sales invoices. management is considering updating its computer with a faster model that would eliminate all of the overtime processing.
Answers: 2
You know the right answer?
A project team using a linear, sequential model builds a software application over a long duration....
Questions
question
Mathematics, 28.05.2021 19:50
question
Mathematics, 28.05.2021 19:50
question
Computers and Technology, 28.05.2021 19:50
Questions on the website: 13722360