A project has a listing of tasks and durations (in days). A(5) starts and is followed by B(7). C(6) follows B. D(2) and E(5) continue after C, so does H(4). Once D, E and H are done, they move to J(2). G(8) starts and flows into H. 1. What are the paths and their durations.
2. What is the critical path?
3. What is the free slack for task B?
4. What is the free slack for task D?
5. What is the free slack for task E?
6. What is the free slack for task H?
7. What is the total slack for task G?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 20:50
Write a method in the heapintpriorityqueue class called merge that accepts another heapintpriorityqueue as a parameter and adds all elements from the other queue into the current queue, maintaining proper heap order such that the elements will still come out in ascending order when they are removed. your code should not modify the queue passed in as a parameter. (recall that objects of the same class can access each other's private fields.)
Answers: 2
question
Computers and Technology, 24.06.2019 12:50
When is it most apprpriate for a development team to change the definition of done
Answers: 1
question
Computers and Technology, 24.06.2019 19:30
Which phrase is the best definition of a pivottable a a table containing data that is organized horizontally b a table used to calculate financial pivot values c a tool used to summarize data d a table containing specific formatting
Answers: 1
question
Computers and Technology, 24.06.2019 22:30
Distinguish between a skill resume and a chronological resume and explain when it is best to use each format
Answers: 1
You know the right answer?
A project has a listing of tasks and durations (in days). A(5) starts and is followed by B(7). C(6)...
Questions
question
Mathematics, 22.09.2021 14:00
question
Biology, 22.09.2021 14:00
Questions on the website: 13722367