A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?
1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 18:30
Which cultural aspect does this type of song best portray? a german polka dance
Answers: 1
question
Computers and Technology, 22.06.2019 21:30
Elements such as fonts colors visual structure graphics and the interface of a web page should complement each other to ensure blank
Answers: 3
question
Computers and Technology, 23.06.2019 01:40
Writing a modular program in visual c++. i am new to this and not sure what i am missing. i am getting the following error: baddate.cpp: in function ‘int main()’: baddate.cpp: 50: 3: error: ‘else’ without a previous ‘if’elsehere are the instructions and code: writing a modular program in c++in this lab, you add the input and output statements to a partially completed c++ program. when completed, the user should be able to enter a year, a month, and a day. the program then determines if the date is valid. valid years are those that are greater than 0, valid months include the values 1 through 12, and valid days include the values 1 through 31.notice that variables have been declared for you.write the simulated housekeeping() function that contains the prompts and input statements to retrieve a year, a month, and a day from the user.include the output statements in the simulated endofjob() function. the format of the output is as follows: month/day/year is a valid date.ormonth/day/year is an invalid date.execute the program entering the following date: month = 5, day = 32, year = 2014. record the output of this program.execute the program entering the following date: month = 9, day = 21, year = 2002. record the output of this /* program name: baddate.cppfunction: this program determines if a date entered by the user is valid.input: interactiveoutput: valid date is printed or user is alerted that an invalid date was entered*/#include bool validatedate(int, int, int); using namespace std; int main(){// declare variablesint year; int month; int day; const int min_year = 0, min_month = 1, max_month = 12, min_day = 1, max_day = 31; bool validdate = true; // this is the work of the housekeeping() method// get the year, then the month, then the daycout< < "enter the year"< > year; cout< < "enter the month"< > month; cout< < "enter the day"< > day; // this is the work of the detailloop() method// check to be sure date is validif(year < = min_year) // invalid yearvaliddate = false; else if (month < min_month || month > max_month) // invalid monthvaliddate = false; else if (day < min_day || day > max_day) // invalid dayvaliddate = false; // this is the work of the endofjob() method// test to see if date is valid and output date and whether it is valid or notif(validdate == true); {// output statementcout<
Answers: 1
question
Computers and Technology, 23.06.2019 08:30
When you interpret the behavior of others according to your experiences and understanding of the world your evaluation is
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Geography, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Physics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
English, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
World Languages, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
question
Mathematics, 13.09.2020 07:01
Questions on the website: 13722363