A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 02:30
Which component acts as a platform on which application software runs
Answers: 2
question
Computers and Technology, 23.06.2019 18:30
The computers in the sales department did not have enough data storage capacity to contain all the information the department needed to store, and it was taking a long time for team members to access the data they needed. to fix the problem, the technician installed new, larger hard drives on all the computers.
Answers: 1
question
Computers and Technology, 24.06.2019 08:30
Aconsumer would pay an extra they used the rent to own program to buy the computer, rather than using cash. for all of the items, is the cheapest option over the life of the contract. the most expensive overall option is to use purchase the item.
Answers: 2
question
Computers and Technology, 24.06.2019 10:00
1. which of these is not true about torsion bars? a. they can be used to adjust ride height b. they can be adjusted anytime since they don't affect alignment angles c. they attach between the frame and the lower control arm d. they twist to produce a spring effect
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Social Studies, 08.09.2021 08:00
question
Mathematics, 08.09.2021 08:00
Questions on the website: 13722363