A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 11:30
Awell-diversified portfolio needs about 20-25 stocks from different categories is this true or false?
Answers: 2
question
Computers and Technology, 22.06.2019 23:30
To check spelling errors in a document, the word application uses the to determine appropriate spelling. internet built-in dictionary user-defined words other text in the document
Answers: 1
question
Computers and Technology, 23.06.2019 02:30
Experimental data that is expressed using numbers is said to be
Answers: 1
question
Computers and Technology, 23.06.2019 11:00
Sports and entertainment class, your goal is to increase attendance and make a profit for a game by getting your team on a winning track with total salaries less than $3,000,000
Answers: 3
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 08.04.2021 23:00
Questions on the website: 13722367