You have a project with four activities as follows. Activity 1 can start immediately and has an estimated duration of 1. Activity 2 can start after activity 1 is completed and has an estimated duration of 4. Activity 3 can start after activity 2 is completed and has an estimated duration of 5. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and activity 4 must be completed before the project is complete. What is the critical path of the project?
A. Start, 1, 2, 3, End
B. Start, 1, 4, 3, End
C. Start, 1, 4, End
D. Start, 1, 2, 3, 4, End

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 20:20
Wireless communications is likely to be viewed as an essential part of an enterprise network infrastructure when: select one: a. mobile communication is needed b. communication facilities must be installed at low initial cost c. communication must take place in a hostile or difficult terrain that makes wired communication difficult or impossible d. the same information must be broadcast to many locations
Answers: 1
question
Computers and Technology, 22.06.2019 19:10
10. when you create a pivottable, you need to specify where to find the data for the pivottable. is it true
Answers: 2
question
Computers and Technology, 23.06.2019 01:00
Let r be a robotic arm with a fixed base and seven links. the last joint of r is a prismatic joint, the other ones are revolute joints. give a set of parameters that determines a placement of r. what is the dimension of the configuration space resulting from your choice of parameters?
Answers: 3
question
Computers and Technology, 24.06.2019 16:30
The database design steps are listed below in the incorrect order. choose the correct order number next to each step. determine the information to be stored in the database. determine the fields needed to record the data determine if there will be any repetition of data entered, and separate the fields into tables to normalize the data. create relationships to connect the tables.
Answers: 3
You know the right answer?
You have a project with four activities as follows. Activity 1 can start immediately and has an esti...
Questions
question
Computers and Technology, 05.10.2019 10:30
Questions on the website: 13722363