What is the critical path?
a. the path from resource to task that passes through all critical components of a project plan
b. the path between tasks to the projects finish that passes through all critical components of a project plan
c. the path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
d. the path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 23:00
In a file-oriented information system, a work file stores relatively permanent data about an entity is created and saved for backup and recovery purposes stores records that contain day-to-day business and operational data is a temporary file created by an information system for a single task
Answers: 1
question
Computers and Technology, 24.06.2019 23:30
What is the opening page of a website called? a. web page b. landing page c. homepage d. opening page
Answers: 1
question
Computers and Technology, 25.06.2019 08:20
The control unit takes ths instructions fetched by the preteched unit and translates them into a form that can be understood by
Answers: 1
question
Computers and Technology, 25.06.2019 13:10
1. which characteristics of pop art are evident in the image? select all that apply. (3 points). a. ben-day dots b. bold use of color c. celebrity figure d. everyday object
Answers: 3
You know the right answer?
What is the critical path?
a. the path from resource to task that passes through all critica...
Questions
question
English, 28.07.2019 01:00
question
Computers and Technology, 28.07.2019 01:00
question
English, 28.07.2019 01:00
Questions on the website: 13722363