Given the following information regarding a project involving an initial public offering (IPO):
Activities Description Duration (weeks) Predecessors
a. Check feasibility 3 —
b. Determine funding 1 —
c. Find possible banks 3 a
d. Select two possible 4 a
e. Interview two banks 4 b
f. Analyze funding costs 5 b
g. Determine chance of success 2 c ,e
h Sign contract 3 f
a) Draw the network.
b) What is the critical path?
c) Calculate the float for each activity.
d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extra weeks?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 23:00
James has set the goal of achieving all "a"s during this year of school.which term best describes this goal
Answers: 2
question
Business, 22.06.2019 02:30
The dollar value generated over decades of customer loyalty to your company is known as brand equity. viability. sustainability. luck.
Answers: 1
question
Business, 22.06.2019 06:30
Individual consumers belong to which step of choosing a target market? possible customers competition demographics communication
Answers: 2
question
Business, 22.06.2019 08:10
Bakery has bought 250 pounds of muffin dough. they want to make waffles or muffins in half-dozen packs out of it. half a dozen of muffins requires 1 lb of dough and a pack of waffles uses 3/4 lb of dough. it take bakers 6 minutes to make a half-dozen of waffles and 3 minutes to make a half-dozen of muffins. their profit will be $1.50 on each pack of waffles and $2.00 on each pack of muffins. how many of each should they make to maximize profit, if they have just 20 hours to do everything?
Answers: 3
You know the right answer?
Given the following information regarding a project involving an initial public offering (IPO):
Questions
question
Advanced Placement (AP), 28.10.2020 16:30
Questions on the website: 13722360