Your organization is in the process of microfilming all the old records in storage. The budget for this process is $500,000 over three years. You have contracted with a company to perform the microfilm services at $0.09 per page and have estimated that there are about 5.5 million pages to be converted. At the end of the first year, you review the invoice and see that you have been billed for converting 2,083,333 pages. Required:
a. Determine your budget variance and what type it is.
b. Provide a short explanation that can be given to administration regarding that variance.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 00:30
Aprice ceiling is “binding” if the price ceiling is set below the equilibrium price. suppose that the equilibrium price is $5. if a price ceiling is set at $6, this will not affect the market in any way since $5 remains a legally allowable price (since $5 < $6). a price ceiling of $6 is called a “non-binding” price ceiling. on the other hand, if the price ceiling is set at $4, the price ceiling is “binding” because the natural equilibrium price is $5 but that is no longer allowed. what happens when there is a binding price ceiling? at a price below the equilibrium price, quantity demanded exceeds quantity supplied. there is a shortage. normally, price increases eliminate shortages by increasing quantity supplied and decreasing quantity demanded. in this case, however, price increases are not allowed past the price ceiling. we therefore predict that the observed market price will be right at the price ceiling and there will be a permanent shortage. the observed quantity bought and sold will be dictated by the quantity supplied at the price ceiling. although consumers would like to buy more, there are no more units for sale
Answers: 1
question
Business, 22.06.2019 04:00
Wallis company manufactures only one product and uses a standard cost system. the company uses a predetermined plantwide overhead rate that relies on direct labor-hours as the allocation base. all of the company's manufacturing overhead costs are fixed—it does not incur any variable manufacturing overhead costs. the predetermined overhead rate is based on a cost formula that estimated $2,886,000 of fixed manufacturing overhead for an estimated allocation base of 288,600 direct labor-hours. wallis does not maintain any beginning or ending work in process inventory.
Answers: 2
question
Business, 22.06.2019 09:30
When you hire an independent contractor you don't have to pay the contractors what
Answers: 3
question
Business, 22.06.2019 13:40
Salge inc. bases its manufacturing overhead budget on budgeted direct labor-hours. the variable overhead rate is $8.10 per direct labor-hour. the company's budgeted fixed manufacturing overhead is $74,730 per month, which includes depreciation of $20,670. all other fixed manufacturing overhead costs represent current cash flows. the direct labor budget indicates that 5,300 direct labor-hours will be required in september. the company recomputes its predetermined overhead rate every month. the predetermined overhead rate for september should be:
Answers: 3
You know the right answer?
Your organization is in the process of microfilming all the old records in storage. The budget for t...
Questions
question
Mathematics, 13.02.2021 21:10
question
Mathematics, 13.02.2021 21:10
Questions on the website: 13722366