A construction company signs a contract with a customer to deliver a new building. The construction company estimates total project revenue of $2 million and total project costs of $1. 5 million. If the construction company spends $1. 2 million in Year 1 of the project, how much REVENUE should the construction company realize in Year 1

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
What is the most important type of decision that the financial manager makes?
Answers: 2
question
Business, 22.06.2019 06:00
List three careers that require knowledge of science. list three careers that require the use of of math. list three careers that require the use of foreign language. list three careers that require the use of good writing skills. list three careers that require the use of good computer skills.
Answers: 3
question
Business, 22.06.2019 10:20
What two things do you consider when evaluating the time value of money
Answers: 1
question
Business, 22.06.2019 11:00
The following transactions occurred during july: received $1,000 cash for services provided to a customer during july. received $4,000 cash investment from bob johnson, the owner of the business received $850 from a customer in partial payment of his account receivable which arose from sales in june. provided services to a customer on credit, $475. borrowed $7,000 from the bank by signing a promissory note. received $1,350 cash from a customer for services to be rendered next year. what was the amount of revenue for july?
Answers: 1
You know the right answer?
A construction company signs a contract with a customer to deliver a new building. The construction...
Questions
question
History, 07.04.2021 18:20
question
Biology, 07.04.2021 18:20
question
Mathematics, 07.04.2021 18:20
question
Social Studies, 07.04.2021 18:20
Questions on the website: 13722367