Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days, but most likely will require 20 days. What is the 20 day estimate called

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:20
Alarge university wanted to study the relationship between completing an internship during college and students' future earning potential. prom the same graduating class, they selected a random sample of 80 students who completed an internship and 100 students who did not complete an internship and examined their salaries five years after graduation. they found that there was a statistically higher mean salary for the internship group than for the noninternship group. which of the following interpretations is the most appropriate? a. there could be a confounding variable, such as student major, that explains the difference in mean salary between the internship and no internship groups.b. we cannot infer anything from these data since the distribution of salaries is likely right skewed.c. you cannot draw any valid conclusions because the sample sizes are different.d. more students should complete internships because having an internship produces a higher salary.
Answers: 1
question
Business, 22.06.2019 22:00
As a general rule, when accountants calculate profit they account for explicit costs but usually ignorea. certain outlays of money by the firm.b. implicit costs.c. operating costs.d. fixed costs.
Answers: 2
question
Business, 23.06.2019 00:30
An emerging methodology to integrate the effort of the development team and the operations team to improve the functionality and security of applications is known as
Answers: 1
question
Business, 23.06.2019 02:00
Present values. the 2-year discount factor is .92. what is the present value of $1 to be received in year 2? what is the present value of $2,000? (lo5-2)
Answers: 3
You know the right answer?
Mauricio estimates that the first module of the project could be completed in as few as 15 days or c...
Questions
question
Chemistry, 11.11.2020 04:10
question
Social Studies, 11.11.2020 04:10
question
Mathematics, 11.11.2020 04:10
question
Health, 11.11.2020 04:10
Questions on the website: 13722367