Activity A begins after the start of the project and has a duration of 5 days. Activity B with a duration of 4 days and Activity D with a duration of 7 days both have Activity A as a predecessor. Activity C with a duration of 3 days is a successor to Activity B. Activity E with a duration of 6 days is a successor to both Activity B and D. Activity H with a duration of 2 days is a successor to both Activity C and Activity E. Activity E also has Activity F with a duration of 8 days as a successor. Activity I with a duration of 9 days is a successor to both Activity H and Activity F. The project finishes after Activity I is completed. The planned duration of the project is:

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
Which of the following best describes how the federal reserve bank banks during a bank run? a. the federal reserve bank has the power to take over a private bank if customers demand too many withdrawals. b. the federal reserve bank can provide a short-term loan to banks to prevent them from running out of money. c. the federal reserve bank regulates exchanges to prevent the demand for withdrawals from rising above the required reserve ratio. d. the federal reserve bank acts as an insurance company that pays customers if their bank fails. 2b2t
Answers: 3
question
Business, 22.06.2019 03:00
Which of the following is not a consideration when determining your asset allocation
Answers: 3
question
Business, 22.06.2019 08:40
Which of the following statements is true regarding the reporting of outside interests and the management of conflicts? investigators are responsible for developing their own management plans for significant financial interests. the institution must report identified financial conflicts of interest to the u.s. office of research integrity. investigators must disclose their significant financial interests related to their institutional responsibilities and not just those related to a particular project. investigators must disclose all of their financial interests regardless of whether they are related to a research project.
Answers: 3
question
Business, 22.06.2019 15:00
Ineed this asap miguel's boss asks him to distribute information to the entire staff about a mandatory meeting. in 1–2 sentences, describe what miguel should do.
Answers: 1
You know the right answer?
Activity A begins after the start of the project and has a duration of 5 days. Activity B with a dur...
Questions
Questions on the website: 13722367