subject
Business, 06.12.2021 23:50 sfigel3160

The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-seat stadium. The construction starts on Monday, February 15, 2016andmustbe completed within 52 weeks. A penalty clause of $15,000 per week for each full or partial of delay beyond this date was written into the contract. Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300,000on the project. He was confident that the project could be completed on time with an allowance made for the usual delays anticipated in such a large project. Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 27. Past experience indicated a fifty–fifty chance of a strike. Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that such a strike would last either eight weeks (70 percent chance) or possibly 12 weeks (30 percent chance). Jim was not pleased with these prospects. However, before he had a chance to discuss contingency plans he was interrupted by Jack White, the vice-president for engineering. Jack commented that a colder December than had been assumed was now being predicted. This factor had not been taken into consideration during earlier estimates since previous forecasts called for milder weather. Concrete pouring in December might thus require in one out of every three cases (depending on the temperature) special heating that costs $500 per week. This additional information did not please Jim at all. The chances for delay were mounting. And an overhead expense of $500 per week would be incurred in case of any delay that exceeds the baseline schedule as defined in Appendix. The technical details of the project are given in the appendix to this case. The management team was asked to consider alternatives for coping with the situation. At the end of the week, four proposals were submitted:

Required:
a. Expedite the pouring of seat gallery supports. This would cost $20,000 and cut the duration of the activity to six weeks.
b. Put a double shift on the filling of the field. A cost of $10,000 would result in a five-week time reduction.
c. The roof is very important since it precedes several activities. The use of three shifts and some overtime could cut six weeks off the roofing at an additional cost of only $9,000.
d. Do nothingAppendix: Technical Details of the StadiumThe stadium is an indoor structure with a seating capacity of 20,000.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 15:20
The beginning inventory is expected to be 2,000 cases. expected sales are 10,000 cases, and the company wishes to begin the next period with an inventory of 1,000 cases. the number of cases the company must purchase during the month is multiple choice 9,000 cases. 10,000 cases. 11,000 cases. 13,000 cases.
Answers: 1
question
Business, 21.06.2019 23:30
The uno company was formed on january 2, year 1, to sell a single product. over a 2-year period, uno’s acquisition costs have increased steadily. physical quantities held in inventory were equal to 3 months’ sales at december 31, year 1, and zero at december 31, year 2. assuming the periodic inventory system, the inventory cost method which reports the highest amount for each of the following is inventory december 31, year 1/ cost of sales year 2 a: lifo fifo b: lifo lifo c: fifo fifo d: fifo lifo
Answers: 3
question
Business, 22.06.2019 07:30
1  2  3  4  5  6  7  8  9  10time remaining59: 30in  the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war? 1 2 3 4 5 6 7 8 9 10time remaining59: 30in the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war?
Answers: 1
question
Business, 22.06.2019 09:30
The 39 percent and 38 percent tax rates both represent what is called a tax "bubble." suppose the government wanted to lower the upper threshold of the 39 percent marginal tax bracket from $335,000 to $208,000. what would the new 39 percent bubble rate have to be? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places,e.g., 32.16.)
Answers: 3
You know the right answer?
The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-sea...
Questions
question
Social Studies, 25.06.2019 00:00
question
Chemistry, 25.06.2019 00:00
question
Mathematics, 25.06.2019 00:00
Questions on the website: 13722361