Assume the following information: Actual run time this week 4,500 minutes
Machine time available this week 4,700 minutes
Actual run rate this week 3.5 units per minute
Ideal run rate 4.0 units per minute
Defect-free output this week 15,000 units
Total output this week (including defects) 15,750 units
The utilization rate is closest to:.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:20
Sye chase started and operated a small family architectural firm in 2016. the firm was affected by two events: (1) chase provided $25,000 of services on account, and (2) he purchased $2,800 of supplies on account. there were $250 of supplies on hand as of december 31, 2016. record the two transactions in the accounts. record the required year-end adjusting entry to reflect the use of supplies and the required closing entries. post the entries in the t-accounts and prepare a post-closing trial balance.
Answers: 1
question
Business, 22.06.2019 16:30
Corrective action must be taken for a project when (a) actual progress to the planned progress shows the progress is ahead of schedule. (b) the technical specifications have been met. (c) the actual cost of the activities is less than the funds received for the work completed. (d) the actual progress is less than the planned progress.
Answers: 2
question
Business, 22.06.2019 19:00
Question 55 ted, a supervisor for jack's pool supplies, was accused of stealing pool supplies and selling them to friends and relatives at reduced prices. given ted's earlier track record, he was not fired immediately. the authorities decided to give him an administrative leave, without pay, until the investigation was complete. in view of the given information, it would be most appropriate to say that ted was: demoted. discharged. suspended. dismissed.
Answers: 2
question
Business, 22.06.2019 19:00
Why is accountability important in managing safety
Answers: 2
You know the right answer?
Assume the following information: Actual run time this week 4,500 minutes
Machine time avai...
Questions
question
Social Studies, 02.07.2019 17:30
Questions on the website: 13722365