Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to-start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags. • Procure prototype parts could start 6 days after the start of Design
• Fabricate parts could start 9 days after the start of Design
• Laboratory test could begin 1 day(s) after the start of Assemble prototype.
• Field test could start 6 days after the start of Laboratory test
• Adjust design could begin 7 days after the start of Field test.
• Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design
• Test unit could begin 9 days after the start of Assemble test production unit.
• Document results could start 3 days after the start of Test unit .
Reconfigure the cyclon schedule by entering all nine start-to-start Tags
What is the ES for Activity D?
What is the LF for Activity H?
What is the slack for Activity C?
What is the slack for Activity H?
What is the slack for Activity I?
What is the length of the project?
What is the critical path?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:30
The following balance sheet for the los gatos corporation was prepared by a recently hired accountant. in reviewing the statement you notice several errors. los gatos corporation balance sheet at december 31, 2018 assets cash $ 44,000 accounts receivable 86,000 inventories 57,000 machinery (net) 122,000 franchise (net) 32,000 total assets $ 341,000 liabilities and shareholders' equity accounts payable $ 54,000 allowance for uncollectible accounts 7,000 note payable 59,000 bonds payable 112,000 shareholders' equity 109,000 total liabilities and shareholders' equity $ 341,000 additional information: cash includes a $22,000 restricted amount to be used for repayment of the bonds payable in 2022. the cost of the machinery is $194,000. accounts receivable includes a $22,000 note receivable from a customer due in 2021. the note payable includes accrued interest of $7,000. principal and interest are both due on february 1, 2019. the company began operations in 2013. income less dividends since inception of the company totals $37,000. 52,000 shares of no par common stock were issued in 2013. 200,000 shares are authorized. required: prepare a corrected, classified balance sheet. (amounts to be deducted should be indicated by a minus sign.)
Answers: 2
question
Business, 22.06.2019 17:00
Jillian wants to plan her finances because she wants to create and maintain her tax and credit history. she also wants to chart out all of her financial transactions for the past federal fiscal year. what duration should jillian consider to calculate her finances? from (march or january )to (december or april)?
Answers: 1
question
Business, 22.06.2019 19:30
Oz makes lion food out of giraffe and gazelle meat. giraffe meat has 18 grams of protein and 36 grams of fat per pound, while gazelle meat has 36 grams of protein and 18 grams of fat per pound. a batch of lion food must contain at least "46,800" grams of protein and 70,200 grams of fat. giraffe meat costs $1/pound and gazelle meat costs $2/pound. how many pounds of each should go into each batch of lion food in order to minimize costs? hint [see example 2.]
Answers: 1
question
Business, 22.06.2019 20:40
Which of the following is true concerning the 5/5 lapse rule? a) the 5/5 lapse rule deems that a taxable gift has been made where a power to withdraw in excess of $5,000 or five percent of the trust assets is lapsed by the powerholder. b) the 5/5 lapse rule only comes into play with a single beneficiary trust. c) amounts that lapse under the 5/5 lapse rule qualify for the annual exclusion. d) gifts over the 5/5 lapse rule do not have to be disclosed on a gift tax return.
Answers: 1
You know the right answer?
Management is not happy with the schedule and wants the project completed as soon as possible. Unfor...
Questions
Questions on the website: 13722367