K. Nelson, project manager of Print... K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software
ID Description Predecessor Time
(days)
A External specifications None 8
B Review design features A 2
C Document new features A 3
D Write software A 60
E Program and test B 40
F Edit and publish notes C 2
G Review manual D 2
H Alpha site E, F 20
I Print manual G 10
J Beta site H, I 10
K Manufacture J 12
L Release and ship K 3
The project is expected to take days
The critical path is
Early Start on activity E is:
Late finish on activity F is:
Slack for activity C is:

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 05:50
Which is one solution to levy the complexity of the global matrix strategy with added customer-focused dimensions?
Answers: 3
question
Business, 22.06.2019 12:30
Consider a treasury bill with a rate of return of 5% and the following risky securities: security a: e(r) = .15; variance = .0400 security b: e(r) = .10; variance = .0225 security c: e(r) = .12; variance = .1000 security d: e(r) = .13; variance = .0625 the investor must develop a complete portfolio by combining the risk-free asset with one of the securities mentioned above. the security the investor should choose as part of her complete portfolio to achieve the best cal would be a. security a b. security b c. security c d. security d
Answers: 3
question
Business, 22.06.2019 16:50
Andrea cujoli is a currency speculator who enjoys "betting" on changes in the foreign currency exchange market. currently the spot price for the japanese yen is ¥129.87/$ and the 6-month forward rate is ¥128.53/$. andrea would earn a higher rate of return by buying yen and a forward contract than if she had invested her money in 6-month us treasury securities at an annual rate of 2.50%. true/false?
Answers: 2
question
Business, 22.06.2019 20:00
Afirm is producing at minimum average total cost with its current plant. draw the firm's long-run average cost curve. label it. draw a point on the lrac curve at which the firm cannot lower its average total cost. draw the firm's short-run average total cost curve that is consistent with the point you have drawn. label it.g
Answers: 2
You know the right answer?
K. Nelson, project manager of Print... K. Nelson, project manager of Print Software, Inc., wants yo...
Questions
Questions on the website: 13722367