On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3
Cost incurred $720,000 $1,170,000 $1,110,000
Expected future costs $1,680,000 $810,000 $0
For this long-term construction contract, the contractor needs to calculate the estimated dollar values of the revenue and gross profit (loss) to be recognized each year.
Complete the contractor's long-term construction contract using the information above.
Revenue Gross Profit (loss)
Year 1
Year 2
Year 3

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 03:00
Match each item to check for while reconciling a bank account with the document to which it relates. (there's not just one answer) 1. balancing account statement 2. balancing check register a. nsf fees b. deposits in transit c. interest earned d. bank errors
Answers: 3
question
Business, 22.06.2019 11:00
%of the world's population controls approximately % of the world's finances (the sum of gross domestic products)" quizlket
Answers: 1
question
Business, 22.06.2019 13:00
Dakota products has a production budget as follows: may, 16,000 units; june, 19,000 units; and july, 24,000 units. each unit requires 3 pounds of raw material and 2 direct labor hours. dakota desires to keep an inventory of 10% of the next month’s requirements on hand. on may, 1 there were 4,800 pounds of raw material in inventory. direct labor hours required in may would be:
Answers: 1
question
Business, 22.06.2019 16:30
Why is investing in a mutual fund less risky than investing in a particular company’s stock?
Answers: 3
You know the right answer?
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expect...
Questions
question
Mathematics, 28.05.2021 01:10
question
Mathematics, 28.05.2021 01:10
question
Mathematics, 28.05.2021 01:10
Questions on the website: 13722363