Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed Job Processing Time (days) Job due date (days)
A 4 7
B 2 4
C 8 11
D 3 5
E 5 11

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 13:00
Matt and his roommate gamal argue repeatedly about wearing shoes in the house versus taking them off at the door. eventually, both are fed up with constantly arguing. they decide to sit down and talk, and not get up until they come to a resolution. this is an example of which decision-making strategy
Answers: 3
question
Business, 21.06.2019 20:30
Which of the following pairs is most similar to each other? a. barter goods and fiat money b. digital money and barter goods c. fiat money and digital money d. commodity money and digital money
Answers: 1
question
Business, 22.06.2019 02:50
Seattle bank’s start-up division establishes new branch banks. each branch opens with three tellers. total teller cost per branch is $96,000 per year. the three tellers combined can process up to 90,000 customer transactions per year. if a branch does not attain a volume of at least 60,000 transactions during its first year of operations, it is closed. if the demand for services exceeds 90,000 transactions, an additional teller is hired and the branch is transferred from the start-up division to regular operations. required what is the relevant range of activity for new branch banks
Answers: 2
question
Business, 22.06.2019 03:00
Which of the following is an effective strategy when interest rates are falling? a. use long-term loans to take advantage of current low rates. b. use short-term loans to take advantage of lower rates when you refinance a loan. c. deposit to a short-term savings instrumentals to take advantage of higher interest rates when they mature. d.select short-term savings instruments to lock in earnings at a current high rates.
Answers: 1
You know the right answer?
Five welding jobs are waiting to be processed. Their processing times and due dates are given below....