The production manager must determine the processing sequence for a total of SEVEN jobs through two machines (M1 and M2) or departments. The same sequence will be allowed in both departments. The manager’s goal is to move the jobs through the two departments as quickly as possible.
(a) Prepare a schedule using SPT for the first department i. e., M1. (1 point)
(b) With the help of a Gantt chart, calculate the total completion time, total idle time and the flowtimes of each job on M1 and M2 using this sequence. (2 points)
(c) Find the optimal sequence using Johnson’s Rule. (1 point)
(d) With the help of a Gantt chart, calculate the total completion time, total idle time and the flowtimes of each job on M1 and M2 using this optimal sequence. (2 points)
Note: You MUST draw a Gantt chart for both sequences in this problem.
Answers: 3
Business, 22.06.2019 06:30
Individual consumers belong to which step of choosing a target market? possible customers competition demographics communication
Answers: 2
Business, 22.06.2019 14:00
How many months does the federal budget usually take to prepare
Answers: 1
Business, 22.06.2019 20:30
Casey communications recently issued new common stock and used the proceeds to pay off some of its short-term notes payable. this action had no effect on the company's total assets or operating income. which of the following effects would occur as a result of this action? a. the company's current ratio increased.b. the company's times interest earned ratio decreased.c. the company's basic earning power ratio increased.d. the company's equity multiplier increased.e. the company's debt ratio increased.
Answers: 3
The production manager must determine the processing sequence for a total of SEVEN jobs through two...
Arts, 12.02.2021 23:10
Mathematics, 12.02.2021 23:10
Mathematics, 12.02.2021 23:10
Mathematics, 12.02.2021 23:10
Geography, 12.02.2021 23:10
Biology, 12.02.2021 23:10
Mathematics, 12.02.2021 23:10
Physics, 12.02.2021 23:10
Mathematics, 12.02.2021 23:10
English, 12.02.2021 23:10