(i) The MPS for product A calls for 80 units to be completed in week 3 and 80 units in week 4 (the lead time is 1 week). The MPS for product B calls for 120 units to be completed in week 5 (the lead time is 2 weeks). (ii) Bill of Material
(iii) Selected Inventory Data
Item
Item
Item
Data Category
C
D
E
Lot sizing rule
L4L
FOQ=180
POQ (P=3)
Lead time (we­eks)
2
1
1
Beginning (on-hand) inventory
30
10
50
Safety stock
0
50
40
Scheduled receipts
190 (wk 2)
180 (wk 1)
80 (wk 1)
Planned order receipts for Item D in week 3 is
a. 0 - 10
b. 150 200
c. 240 - 300
d. 350 - 450
e. None of the above

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 13:30
Who collects federal taxes? a. irs b. ins c. treasury d. federal reserve
Answers: 2
question
Business, 22.06.2019 12:30
Suppose a holiday inn hotel has annual fixed costs applicable to its rooms of $1.2 million for its 300-room hotel, average daily room rents of $50, and average variable costs of $10 for each room rented. it operates 365 days per year. the amount of operating income on rooms, assuming an occupancy* rate of 80% for the year, that will be generated for the entire year is *occupancy = % of rooms rented
Answers: 1
question
Business, 22.06.2019 13:30
If the economy were in the contracting phase of the business cycle, how might that affect your ability to find work?
Answers: 2
question
Business, 22.06.2019 18:10
Find the zeros of the polynomial 5 x square + 12 x + 7 by factorization method and verify the relation between zeros and coefficient of the polynomials
Answers: 1
You know the right answer?
(i) The MPS for product A calls for 80 units to be completed in week 3 and 80 units in week 4 (the l...
Questions
question
Mathematics, 14.10.2019 16:00
question
Mathematics, 14.10.2019 16:00
Questions on the website: 13722363