Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cost elements into a final bid price to the customer. What is the total cost for the project? How long will the project take to complete? Function points in the project: 252
Software engineers assigned to this team: 5
Function point productivity per software engineer: 5 per month
Workdays per typical month: 22
Productivity hours per typical workday: 8
Gross Hourly wage rate per software engineer (does not include fringe benefits): 50
Overhead (fringe benefit, other direct overhead) rate: 40%
G&A rate: 11.5%
Proposed Profit: 15%

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 15:30
Calculate the required rate of return for climax inc., assuming that (1) investors expect a 4.0% rate of inflation in the future, (2) the real risk-free rate is 3.0%, (3) the market risk premium is 5.0%, (4) the firm has a beta of 2.30, and (5) its realized rate of return has averaged 15.0% over the last 5 years. do not round your intermediate calculations.
Answers: 3
question
Business, 22.06.2019 16:30
:; )write a paragraph of two to three sentences and describe what will happen to a society that does not have a productive workforce?
Answers: 3
question
Business, 22.06.2019 20:20
Why is it easier for new entrants to get involved in radical innovations when compared to incumbent firms? a. unlike incumbent firms, new entrants do not have to face the high entry barriers, initially. b. new entrants are embedded in an innovation ecosystem, while incumbent firms are not. c. unlike incumbent firms, new entrants do not have formal organizational structures and processes. d. incumbent firms do not have the advantages of network effects that new entrants have.
Answers: 2
question
Business, 22.06.2019 22:50
What is the difference between the contractual interest rate and the market interest rate?
Answers: 1
You know the right answer?
Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cos...
Questions
question
Biology, 18.03.2021 03:30
question
Mathematics, 18.03.2021 03:30
question
Biology, 18.03.2021 03:30
question
English, 18.03.2021 03:30
question
Mathematics, 18.03.2021 03:30
Questions on the website: 13722362