Curtiss Construction Company, Inc. entered into a fixed-price contract with Axelrod Associates on July 1, 2015, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2017. Accumulatedcontract costs incurred, estimated costs to complete the contract, accumulated billings to Axelrod and cash collections from Axelrod under the contract are as follows: 12/31/2015 12/31/2016 12/31/2017
Costs incurred (to date) $350,000 $2,500,000 $4,250,000
Estimated costs to complete 3,150,000 1,700,000 0
Billings to Axelrod (to date) 720,000 2,170,000 3,600,000
Cash collections (to date) 600,000 1,800,000 3,600,000
Required:
1. For each of the three years, prepare a schedule to compute total gross profit or loss to be recognized as a result of this contract.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2016 and 2017 as either cost in excess of billings or billings in excess of costs.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 05:30
The hartman family is saving $400 monthly for ronald's college education. the family anticipates they will need to contribute $20,000 towards his first year of college, which is in 4 years .which best explain s whether the family will have enough money in 4 years ?
Answers: 1
question
Business, 22.06.2019 08:30
What is the key to success in integrating both lethal and nonlethal activities during planning? including stakeholders once a comprehensive operational approach has been determined knowing the commander's decision making processes and "touch points" including stakeholders from the very beginning of the design and planning process including the liaison officers (lnos) in all the decision points?
Answers: 1
question
Business, 22.06.2019 22:30
The answer here, x=7, is not in the interval that you selected in the previous part. what is wrong with the work shown above?
Answers: 1
question
Business, 23.06.2019 00:00
What is a sales lead? a. an employee on the customer service team who deals with existing customers b. a sales person who works on a residual commission structure c. an expert in maslow's hierarchy of needs d. a potential customer who has shown interest in the company's product
Answers: 1
You know the right answer?
Curtiss Construction Company, Inc. entered into a fixed-price contract with Axelrod Associates on Ju...
Questions
question
Mathematics, 30.10.2020 21:40
question
English, 30.10.2020 21:40
Questions on the website: 13722363