A coal-fired power plant can produce electricity at a variable cost of $0.07 per kilowatt-hour when running at its full capacity of 30 megawatts per hour, $0.16 per kilowatt-hour when running at 20 megawatts per hour, and $0.24 per kilowatt-hour when running at 10 megawatts per hour. A gas-fired power plant can produce electricity at a variable cost of $0.12 per kilowatt-hour at any capacity from 1 megawatt per hour to its full capacity of 5 megawatts per hour. The cost of constructing a coal-fired plant is $70 million, but it costs only $14 million to build a gas-fired plant. Required:
a. Consider a city that has a peak afternoon demand of 80 megawatts of electricity. If it wants all plants to operate at full capacity, what combination of coal-fired plants and gas-fired plants would minimize construction costs?
b. How much will the city spend on building that combination of plants?
c. What will the average cost per kilowatt-hour be if you average over all 80 megawatts that are produced by that combination of plants?

ansver
Answers: 1

Another question on Business

question
Business, 20.06.2019 18:02
All mathematical operations can be performed on ratio data. a. true b. false
Answers: 1
question
Business, 22.06.2019 10:40
You were able to purchase two tickets to an upcoming concert for $100 apiece when the concert was first announced three months ago. recently, you saw that stubhub was listing similar seats for $225 apiece. what does it cost you to attend the concert?
Answers: 1
question
Business, 22.06.2019 11:10
An insurance company estimates the probability of an earthquake in the next year to be 0.0015. the average damage done to a house by an earthquake it estimates to be $90,000. if the company offers earthquake insurance for $150, what is company`s expected value of the policy? hint: think, is it profitable for the insurance company or not? will they gain (positive expected value) or lose (negative expected value)? if the expected value is negative, remember to show "-" sign. no "+" sign needed for the positive expected value
Answers: 2
question
Business, 22.06.2019 19:00
When making broccoli cream soup, the broccoli and aromatics should be a. burned. b. simmered. c. puréed. d. sweated.
Answers: 2
You know the right answer?
A coal-fired power plant can produce electricity at a variable cost of $0.07 per kilowatt-hour when...
Questions
question
Mathematics, 09.07.2019 02:50
question
English, 09.07.2019 02:50
question
Mathematics, 09.07.2019 02:50
question
Mathematics, 09.07.2019 02:50
question
Spanish, 09.07.2019 02:50
Questions on the website: 13722367