Determine the number of containers required to support a lean process which uses 150 parts per hour. The time for a container to complete a cycle (move, wait, empty, return, fill) is 0.75 hours. A single container has a capacity of 6 parts. An inefficiency factor of 0.12 is currently being used. (Round any fractional result up to the next higher whole number.)

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 04:50
Harwood company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. the company's predetermined overhead rate of $2.50 per machine-hour was based on a cost formula that estimates $240,000 of total manufacturing overhead for an estimated activity level of 96,000 machine-hours. required: 1. assume that during the year the company works only 91,000 machine-hours and incurs the following costs in the manufacturing overhead and work in process accounts: compute the amount of overhead cost that would be applied to work in process for the year and make the entry in your t-accounts. 2a. compute the amount of underapplied or overapplied overhead for the year and show the balance in your manufacturing overhead t-account. 2b. prepare a journal entry to close the company's underapplied or overapplied overhead to cost of goods sold.
Answers: 1
question
Business, 22.06.2019 20:40
Which of the following is true concerning the 5/5 lapse rule? a) the 5/5 lapse rule deems that a taxable gift has been made where a power to withdraw in excess of $5,000 or five percent of the trust assets is lapsed by the powerholder. b) the 5/5 lapse rule only comes into play with a single beneficiary trust. c) amounts that lapse under the 5/5 lapse rule qualify for the annual exclusion. d) gifts over the 5/5 lapse rule do not have to be disclosed on a gift tax return.
Answers: 1
question
Business, 23.06.2019 00:00
According to the video, the gross national product had declined from $104 billion in 1929 to about in 1933.
Answers: 2
question
Business, 23.06.2019 00:30
Emerson has an associate degree. based on the bar chart below,how will his employment opportunities change from 2008 to 2018
Answers: 2
You know the right answer?
Determine the number of containers required to support a lean process which uses 150 parts per hour....
Questions
question
Mathematics, 23.05.2021 01:00
question
Mathematics, 23.05.2021 01:00
question
Mathematics, 23.05.2021 01:00
question
Mathematics, 23.05.2021 01:00
question
Mathematics, 23.05.2021 01:00
question
Business, 23.05.2021 01:00
question
English, 23.05.2021 01:00
question
Mathematics, 23.05.2021 01:00
Questions on the website: 13722366