What must a project manager do before creating a dependency schedule?

a. identify which tasks must be completed by the project manager.
b. identify which tasks will involve the most teamwork.
c. identify which tasks can be skipped.
d. identify which tasks are primary and which are dependent.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:30
On june 1, 2017, blossom company was started with an initial investment in the company of $22,360 cash. here are the assets, liabilities, and common stock of the company at june 30, 2017, and the revenues and expenses for the month of june, its first month of operations: cash $4,960 notes payable $12,720 accounts receivable 4,340 accounts payable 840 service revenue 7,860 supplies expense 1,100 supplies 2,300 maintenance and repairs expense 700 advertising expense 400 utilities expense 200 equipment 26,360 salaries and wages expense 1,760 common stock 22,360 in june, the company issued no additional stock but paid dividends of $1,660. prepare an income statement for the month of june.
Answers: 3
question
Business, 22.06.2019 15:30
Uknow what i love about i ask a dumb question it is immediately answered but when i ask a real question it take like an hour to get answered
Answers: 2
question
Business, 22.06.2019 17:30
Kevin and jenny, who are both working full-time, have three children all under the age of ten. the two youngest children, who are three and five years old, attended eastside pre-school for a total cost of $3,000. ervin, who is nine, attended big kid daycare after school at a cost of $2,000. jenny has earned income of $15,000 and kevin earns $14,000. what amount of childcare expenses should be used to determine the child and dependent care credit?
Answers: 3
question
Business, 23.06.2019 02:20
Speedy auto repairs uses a job-order costing system. the company’s direct materials consist of replacement parts installed in customer vehicles, and its direct labor consists of the mechanics’ hourly wages. speedy’s overhead costs include various items, such as the shop manager’s salary, depreciation of equipment, utilities, insurance, and magazine subscriptions and refreshments for the waiting room. the company applies all of its overhead costs to jobs based on direct labor-hours. at the beginning of the year, it made the following estimates: direct labor-hours required to support estimated output 20,000 fixed overhead cost $ 350,000 variable overhead cost per direct labor-hour $ 1.00 required: 1. compute the predetermined overhead rate. 2. during the year, mr. wilkes brought in his vehicle to replace his brakes, spark plugs, and tires. the following information was available with respect to his job: direct materials $ 590 direct labor cost $ 109 direct labor-hours used 6
Answers: 1
You know the right answer?
What must a project manager do before creating a dependency schedule?

a. identify which...
Questions
Questions on the website: 13722367