Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities is A- 3.5 months

B- 5.7 months

C - 1.6 months

D- 2.1 months

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:40
Nikolas works in a shoe store as a salesperson. a teenage boy comes in looking for comfortable sports shoes because he is going on a hike. he tells nikolas he wants shoes that have velcro straps. nikolas shows him a wide variety of velcro-strapped shoes, but the customer rejects them because they don't feel comfortable. he asks for sports shoes with laces instead. nikolas once again shows him a wide variety. the boy is once again not satisfied and asks to see the velcro-strapped shoes again. nikolas is irritated but doesn't show his annoyance. what customer service skill is nikolas showing? nikolas is a. meekness b. patience c. persistence
Answers: 1
question
Business, 22.06.2019 01:00
In order to gauge public opinion about how to handle iran's growing nuclear program, a research group surveyed 1010 americans by telephone and asked them to rate the threat iran's nuclear program poses to the world on a scale of 1 to 10. describe the population, sample, population parameters, and sample statistics. identify the population in the given problem. choose the correct answer below.
Answers: 2
question
Business, 22.06.2019 04:10
Lynch company manufactures and sells a single product. the following costs were incurred during the company’s first year of operations: variable costs per unit: manufacturing: direct materials $ 12 direct labor $ 6 variable manufacturing overhead $ 1 variable selling and administrative $ 1 fixed costs per year: fixed manufacturing overhead $ 308,000 fixed selling and administrative $ 218,000 during the year, the company produced 28,000 units and sold 15,000 units. the selling price of the company’s product is $56 per unit. required: 1. assume that the company uses absorption costing: a. compute the unit product cost. b. prepare an income statement for the year. 2. assume that the company uses variable costing: a. compute the unit product cost. b. prepare an income statement for the year.
Answers: 1
question
Business, 22.06.2019 05:50
Which is one solution to levy the complexity of the global matrix strategy with added customer-focused dimensions?
Answers: 3
You know the right answer?
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the...
Questions
question
English, 08.01.2020 02:31
Questions on the website: 13722363