Which of the following are characteristics of a well-designed and effectively functioning change management and change control process? a. Senior management review and approval of major changes.
b. Conversion controls to ensure that data is completely and accurately transferred to the new system.
c. Monitoring of how changes affect segregation of duties.
d. Development of "backout" plans in the event a change creates unexpected problems.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
Which of the following is an example of formal management controls? answers: a firm's culturethe willingness of employees to monitor each otherbudgeting and reporting activitiesmanagerial motivation
Answers: 3
question
Business, 22.06.2019 08:30
Match the given situations to the type of risks that a business may face while taking credit. 1. beta ltd. had taken a loan from a bank for a period of 15 years, but its sales are gradually showing a decline. 2. alpha ltd. has taken a loan for increasing its production and sales, but it has not conducted any research before making this decision. 3. delphi ltd. has an overseas client. the economy of the client’s country is going through severe recession. 4. delphi ltd. has taken a short-term loan from the bank, but its supply chain logistics are not in place. a. foreign exchange risk b. operational risk c. term of loan risk d. revenue projections risk
Answers: 3
question
Business, 22.06.2019 11:10
Your team has identified the risks on the project and determined their risk score. the team is in the midst of determining what strategies to put in place should the risks occur. after some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. which of the following is true regarding this question? a. this is a positive response strategy.b. this is a negative response strategy.c. this is a response strategy for either positive or negative risk known as contingency planning.d. this is a response strategy for either positive or negative risks known as passive acceptance.
Answers: 2
question
Business, 23.06.2019 01:00
What is the average price for the cordless telephones (to 2 decimals)? $ b. what is the average talk time for the cordless telephones (to 3 decimals)? hours c. what percentage of the cordless telephones have a voice quality of excellent? % d. what percentage of the cordless telephones have a handset on the base?
Answers: 3
You know the right answer?
Which of the following are characteristics of a well-designed and effectively functioning change man...
Questions
question
English, 15.10.2019 14:10
question
Mathematics, 15.10.2019 14:10
question
Mathematics, 15.10.2019 14:10
question
World Languages, 15.10.2019 14:10
Questions on the website: 13722367