Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 260,000 Fixed manufacturing overhead cost $ 5,720,000 Variable manufacturing overhead cost per machine-hour $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the customer for $4,400. The following information was available with respect to this job: Direct materials $ 2,024 Direct labor cost $ 1,452 Machine-hours used 91 Compute the total manufacturing cost assigned to Job P90.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 23:00
James has set the goal of achieving all "a"s during this year of school.which term best describes this goal
Answers: 2
question
Business, 22.06.2019 06:30
Select all that apply. select the ways that labor unions can increase wages. collective bargaining reducing the labor supply increasing the demand for labor creating monopolies
Answers: 1
question
Business, 22.06.2019 08:00
Why do police officers get paid less than professional baseball players?
Answers: 2
question
Business, 22.06.2019 11:00
Alocal barnes and noble bookstore ordered 80 marketing books but received 60 books. what percent of the order was missing?
Answers: 1
You know the right answer?
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a...
Questions
question
Mathematics, 09.10.2019 15:00
Questions on the website: 13722360