Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note
$7,000,000, 7% bonds
Construction expenditures incurred were as follows:
July 1, 2021 $ 700,000
September 30, 2021 990,000
November 30, 2021 990,000
January 30, 2022 930,000
The company’s fiscal year-end is December 31.
Required:
Calculate the amount of interest capitalized for 2021 and 2022.
Calculate the amount of interest capitalized for 2021.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 13:30
The average daily foreign exchange trading by banks around the world is closest to $ a. 1.5 trillion b. 1 trillion c. 600 billion d. 700 billion e. 1.3 trillion
Answers: 1
question
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
question
Business, 23.06.2019 02:30
How is the role of government determined in the american free enterprise system?
Answers: 2
question
Business, 23.06.2019 19:30
Common law reflects how society is ever changingm
Answers: 1
You know the right answer?
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...
Questions
question
English, 12.03.2020 17:23
question
Mathematics, 12.03.2020 17:23
Questions on the website: 13722363