There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows: Job (Hours)
Resource A B C D
1 5 8 7 7
2 4 9 5 9
3 6 9 8 7
4 7 6 6 9
What is the optimal assignment of resources to jobs?
Multiple Choice
1 to A; 2 to C; 3 to B; 4 to D
1 to B; 2 to D; 3 to C; 4 to A
1 to C; 2 to B; 3 to A; 4 to D
1 to D; 2 to B; 3 to C; 4 to A
1 to A; 2 to C; 3 to D; 4 to B

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:00
You speak to a business owner that is taking in almost $2000 in revenue each month. the owner still says that they are having trouble keeping the doors open. how can that be possible? use the terms of revenue, expenses and profit/loss in your answer
Answers: 3
question
Business, 22.06.2019 11:00
Zoe would like to be able to save for night courses at the local college. which of these would be a good way for zoe to make more money available for savings without dramatically changing her budget? economía
Answers: 2
question
Business, 22.06.2019 15:00
Oerstman, inc. uses a standard costing system and develops its overhead rates from the current annual budget.the budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours.(practical capacity is 500,000 hours)annual budgeted overhead costs total $772,800, of which $556,800 is fixed overhead.a total of 119,300 units, using 478,000 direct labor hours, were produced during the year.actual variable overhead costs for the year were $260,400 and actual fixed overhead costs were $555,450.required: 1. compute the fixed overhead spending variance and indicate if favorable or unfavorable.2. compute the fixed overhead volume variance and indicate if favorable or unfavorable.
Answers: 3
question
Business, 22.06.2019 16:10
Answer the following questions using the banker’s algorithm: a. illustrate that the system is in a safe state by demonstrating an order in which the processes may complete. b. if a request from process p1 arrives for (1, 1, 0, 0), can the request be granted immediately? c. if a request from process p
Answers: 1
You know the right answer?
There are four resources and four jobs to be done. Assume there must be one-to-one matching between...
Questions
Questions on the website: 13722367