Business, 27.12.2020 16:40 celestesanchezts
Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below:
Bid price $450,000
Contract cost:2020 (180,000)
2021 (195,000)
Gross profit: 75,000
Estimated cost to complete:
12/31/2020$200,000
12/31/2021 0
Assuming BCC recognizes revenue over time according to percentage of completion for this contract, the gross profit recognized in 2020 would be (rounded to the nearest thousand):
A.) 33,000
B.) 36,000
C.) 69,000
D.) 30,000
Answers: 3
Business, 22.06.2019 00:10
Which of the following is a problem for the production of public goods?
Answers: 2
Business, 22.06.2019 10:50
Melissa is a very generous single woman. before this year, she had given over $11,400,000 in taxable gifts over the years and has completely exhausted her applicable credit amount. in the current year, melissa gave her daughter riley $100,000 and promptly filed her gift tax return. melissa did not make any other gifts this year. how much gift tax must riley pay the irs because of this transaction?
Answers: 2
Business, 22.06.2019 12:00
Identify at least 3 body language messages that project a positive attitude
Answers: 2
Business, 22.06.2019 14:30
The face of a company is often that of the lowest paid employees who meet the customers. select one: true false
Answers: 1
Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presen...
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Physics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31
Mathematics, 26.11.2019 06:31